I recently came across this article by Josh Odgers. Good writeup on how to monitor and watch for CPU ready issues within your environment.
What is CPU Ready?
CPU ready is basically the time it takes a VM to be scheduled onto physical
core after it is placed in the CPU scheduling queue.
What is High CPU Ready?
In my opinion, during peak load, anything above 2% (or 400ms) is a concern
and should be monitored. Above 5% will be impacting performance (resulting in
lower CPU utilization) and 10% or more, should be considered a serious problem
and remediated immediately.
The below is a screenshot showing CPU ready from a recent test I conducted in
my home lab
To calculate the percentage of CPU Ready, we divide the VMs “Summation” value
(in the screen shot above its the “W2K8 CPU TEST VM 1″ line by 20000 (ms) which
is the statistics collection interval, then divide the result by the number of
vCPUs in the VM.
So if we use the value from the “latest” column, its 7337 divide 20000,
equals : 0.36685, then we divide that by 2 as the VM has 2 vCPUs and we end up
with 0.183425
That’s 18% CPU Ready, which basically means 18% of the time, the VM is not
doing anything!
Note: CPU Ready % can be found using ESXTOP or RESXTOP via the vMA or on the
ESXi host directly.
Now to try and diagnose the Performance/CPU ready issue, we need to work out
if the VM is oversized and if so, Right Size the VM.
What is an Oversized VM?
Basically a VM which has more compute resources assigned than it requires,
for example, a VM which uses no more than 20% of its CPU and has 4
vCPUs.
What is Right Sizing?
In the above example, the VM is oversized as it doesn’t use more than 1vCPU
(or 25%) of the CPU resources and therefore could be reduced to to 1 vCPU and
run at 80%.
So the VM is oversized, and has High CPU ready, what happens when
we right size it from 4vCPUs to 1vCPU and why does this help performance?
Its
pretty simple, the less vCPUs a VM has, the easier job the CPU scheduler has to
find enough physical cores to schedule the VM onto. If a cluster has a lot of
oversized VMs, all the VMs are all competing for the same physical cores, and
making it more and more difficult for the scheduler.
But what about setting a CPU Reservation? Don’t reservations “guarantee”
resources?
The answer is, Yes and No.
The reservation “reserves” CPU resources measured in Mhz, but this has
nothing to do with the CPU scheduler.
So setting a reservation will help improve performance for the VM you set it
on, but will not “solve” CPU ready issues caused by “oversized” VMs, or by too
high an overcommitment ratio of CPU resources.
In my testing I set an 80% reservation of a VMs 2 vCPUs worth of Mhz and
prior to setting the reservation the CPU ready was ~20% and then CPU Ready did
drop to around 10%.
Note: This test was performed with only 25% overcommitment –
5 vCPUs on 4 physical Cores using CPUBUSY to keep the CPUs running at 100%
(measured within the guest by Windows Task Manager). I then set a 100% reservation of the VMs 2 vCPUs worth of Mhz, prior to
setting the reservation the CPU ready was ~10% and CPU Ready did not get below
2.5% even with 100% reservation.
The result would have been exponentially worse had I tested with 50% or 100%
overcommitment which is generally easily achieved with VMware and a well
architected cluster. (I have seen well above these overcommitment numbers with
no CPU ready issues).
Reducing CPU Ready down to 2.5% may sound like a pretty good result, but when
we look at the other 3 x 1vCPU VMs on the host (4 core test ESXi 5 host) they
had CPU ready of 40%!! Not to mention 2.5% is still not good!
If you have poor performance, and you discover you have High CPU Ready the
best solution is
Right Size Your VMs!
I have recommended exactly that countless times and the customers never
believe that performance can increase with less vCPUs, until after the Right
Sizing exercise. If after Right sizing, you still have CPU Ready, your overcommitment on CPU
is simply to high for the workloads within your cluster.
You can address this by
1. Adding additional compute to the cluster. (Duh!)
2. Using Affinity rules to locate complimentary workloads together (Lots of
small 1vCPU VMs which don’t have high CPU utilization will generally work well
with a limited number of higher vCPU VMs)
3. Use Anti-Affinity rules to separate non complimentary workloads (eg: Don’t
place all your 8vCPU VMs on one host with 300% overcommitment on CPU and expect
them to work well).
4. Scaling out (not up) your VMs ie: Don’t have one 8 vCPU SQL DB server, use
4 smaller 2vCPU VMs
So now you know better than to use reservations to solve CPU contention.